Sign Up for Vincent AI
BRB Contractors, Inc. v. Web Water Dev. Ass'n
Pending before the Court is Plaintiff BRB Contractors, Inc.'s ("BRB") Motion for Partial Summary Judgment seeking an order from the Court that any damages suffered by Defendant WEB Water Development Association, Inc. ("WEB") from its counterclaim alleging breach of contract are limited to "the reasonable cost of restoration, unless such cost is greater than the diminution in value of the [ ] premises, in which case the difference in market value before and after injury would be the proper measure of damages." (Doc. 32 at 1) (quoting Reed v. Consolidated Feldspar Corp., 23 N.W.2d 154, 157 (S.D. 1946)). In addition, in its Motion, BRB asks the Court to rule that WEB has not sustained any damages related to the post-construction condition of the landowners' topsoil conditions because WEB voluntarily incurred costs to reclaim the topsoil without claims or lawsuits asserted by the landowners. For the following reasons, BRB's Motion for Partial Summary Judgment is denied.
BACKGROUND
WEB Water Development Association, Inc. ("WEB") is rural water system containing approximately 6,800 miles of pipe spanning an area approximately 9,300 square miles. (Doc. 38, ¶ 2). WEB, as the owner, and BRB Contractors, Inc. ("BRB"), as the contractor, entered into a written contract effective August 24, 2017 (the "Contract") for the construction of a 3-mile underground water pipeline near Bowdle, South Dakota ("the Project"). (Docs. 33, ¶ 1; 35, ¶ 1). WEB separately retained DGR Engineering ("DGR") to serve as the Project Engineer for the Project. (Docs. 33, ¶ 2; 35, ¶ 2).
The Project crosses 6 farms and WEB acquired pipeline easements from each of the fee-simple landowners for the construction of the Project, as well as temporary easements to access the construction sites. (Docs. 33, ¶ 3; 35, ¶ 3; 34-2, Hammrich Dep. 16:5-9). WEB did not pay any compensation to the landowners to obtain the easements. (Docs. 33, ¶ 4; 35, ¶ 4).
The Contract provides that BRB will complete all work as specified in the Contract Documents, including specifications detailed in the Project Manual, and that WEB will make progress payments prior to Substantial Completion of the Project. (Docs. 34-1 at A-1, A-5). Upon Substantial Completion, the Contract provides that WEB "shall pay BRB an amount sufficient to increase total payments to [BRB] to 95 percent of the Work completed, less such amounts set off by [WEB] pursuant to Paragraph 15.01.E of the General Conditions, and less 200 percent of Engineer's estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment." (Doc. 34-1 at A-3). The Project Manual prepared by DGR provided that "[t]opsoil shall be salvaged and replaced on the trenches to a minimum depth of 6" and shall be graded and shaped to original condition." (Doc. 40-6 at 2-14). Per the Contract's terms, BRB was required to add topsoil if necessary to meet completed requirements. (Doc. 40-6 at 2-31). Topsoil is defined by the Contract as "soil typical of the area, which is capable of supporting native plant growth." (Doc. 40-6 at 2-32).
WEB does not have any agreements with landowners concerning the quality of the topsoil on the easements after construction, but made crop reimbursement payments to certain landowners for the 2018 season. (Docs. 33, ¶¶ 5, 7; 35, ¶¶ 5, 7). BRB is not obligated to pay the landowners or reimburse WEB for those crop reimbursement payments (Docs. 33, ¶ 5; 35, ¶ 5).
On November 1, 2018, representatives of WEB, BRB, and DGR conducted the final walkthrough for the Project. (Docs. 33, ¶ 8; 35, ¶ 8). WEB agreed that all items on the punch list dated November 1, 2018, had been completed except for items 4 and 11, both of which were to be completed later in the warranty period. (Docs. 33, ¶ 8; 35, ¶ 8). Although the punch list did not mention the condition of the topsoil, that subject had previously been brought to the attention of BRB prior to November 1, 2018. (Docs. 33, ¶ 8; 35, ¶ 8). Specifically, on June 5, 2018, DGR prepared a daily field observation report in which BRB was "reminded of the 6" minimum topsoil specification" found in the Project Manual. (Doc. 40-2, Pabolo Dep. 17:16-18:23). WEB had received complaints from some landowners about the Project and the condition of the topsoil overthe easements. Specifically, on September 20, 2018, one of the landowners wrote to WEB informing them of the following:
(Doc. 40-1). Dustin Pabolo, the onsite foreman for the Project, recalls that a section of pipe was dug up several times because the water service kept breaking. (Doc. 40-2, Pabolo Dep. 5:18-20; 28:2-19). Mr. Pabolo testified that soil was insufficient to support the weight of the water service on the vertical 1-inch line which had snapped under the weight. (Doc. 40-2, Pabolo Dep. 28:2:19).
On November 2, 2018, after the final walkthrough, WEB notified DGR that one of the landowners had called WEB "regarding topsoil issues," and DGR engineer Nathan Brandenburg emailed that information to BRB employee Brandon Pabolo. (Docs. 33, ¶ 9; 35, ¶ 9). On November 14, 2018, DGR engineer Nathan Brandenburg sent WEB employee Eric Hansen an email that stated:
(Docs. 33, ¶ 11; 35, ¶ 11). In response to Mr. Brandenburg's email, Mr. Hansen replied:
On November 13, 2018, WEB received a proposal from a construction company in Aberdeen to correct the topsoil issues and on December 3, 2018, received another estimate from B&B Contracting for $151,000 to remedy topsoil issues in 7,920 lineal feet of the easement across the Dewalds' and Hubers' property. (Doc. 34-2, Hammrich Dep. 60:7-61:20).
On December 3, 2018, BRB informed Nathan Brandenburg at DGR by email that he had reached verbal agreements with two landowners, the Hubers and the Dewalds, resolving potential topsoil issues. (Docs. 33, ¶ 10; 35, ¶ 10; 40-7). Specifically, BRB and the Hubers verbally agreed that BRB would provide the Hubers with eight to ten loads of topsoil to correct any topsoil deficiencies on their property. (Doc. 34-7 at 4; 40-7). BRB would pay Hubers for their time and equipment to spread the topsoil. (Doc. 40-7). BRB's agreement with the Dewalds was to have a neighbor rip his field in the spring as he felt his ground was too compacted and disk in manure. (Doc. 40-7).
When this December 3, 2018, email was passed along to Ms. Hammich at WEB, she inquired whether BRB's proposal adheres to the specifications in the Contract and Mr. Brandenburg responded as follows:
The specifications do not require a specific method for fixing a top soil issue. Which goes back to not controlling means and methods. The specifications callout an end product and in this case, a minimum depth of 6 inches of topsoil and no greater than 12" of grade change above the trench (which cannot extend more than 2 feet on either side of the trench and must provide adequate drainage). For your information I am referencing Section 02221, Paragraphs 3.05.C.2.b and 3.05.C.5. Section 02246 Paragraph 2.01.B. says that topsoil is considered to mean soil typical of the area, which is capable of supporting native plant growth. At this point I don't believe we know enough to say if there...
Experience vLex's unparalleled legal AI
Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting