Case Law Controlled Environments Construction, Inc. v. Key Industrial Refrigeration Co.

Controlled Environments Construction, Inc. v. Key Industrial Refrigeration Co.

Document Cited Authorities (41) Cited in Related

Appeal from the District Court for Douglas County: J. Patrick Mullen, Judge. Affirmed in part, and in part reversed and remanded for further proceedings.

David S. Houghton and J.P. Sam King, of Lieben, Whitted, Houghton, Slowiaczek & Cavanagh, P.C., L.L.O., for appellant.

Mary Kay Frank, of Cline, Williams, Wright, Johnson & Oldfather, and Brian W. McGrath and G. Michael Halfenger, of Foley & Lardner, for appellee Hill-Phoenix, Inc.

Michael A. Nelsen, of Hillman, Forman, Nelsen, Childers & McCormack, for appellee Key Industrial Refrigeration Co.

Hendry, C.J., Connolly, Gerrard, Stephan, and Miller-Lerman, JJ.

Gerrard, J.

I. NATURE OF CASE

Controlled Environments Construction, Inc. (CEC), sued Key Industrial Refrigeration Co. (Key) and Hill-Phoenix, Inc., for breaches of contract and warranty arising out of two separate construction contracts to build refrigeration facilities in Omaha, Nebraska, and Minot, North Dakota. Essentially, CEC alleged that Hill-Phoenix sold defective refrigeration equipment to Key and that Key then sold that equipment to CEC for use in the construction projects they were undertaking for Food Services of America, Inc. (FSA). Only the warranty claims arising out of the Minot project are at issue in this appeal.

The district court determined that the Hill-Phoenix warranty extended to future performance and that the breach of warranty was or should have been discovered by CEC by January or February 1994. As such, the court concluded that CEC's warranty claims—filed in July 1998—were barred by the 4-year statute of limitations for the sale of goods, Neb. U.C.C. § 2-725 (Reissue 2001), and entered summary judgments for Hill-Phoenix and Key. CEC appeals.

II. FACTUAL AND PROCEDURAL BACKGROUND

In June 1992, CEC contracted with FSA to construct a building in Omaha. In June 1993, CEC entered into a second contract with FSA to construct a similar building in Minot. Shortly thereafter, CEC entered into agreements with Key. Under these agreements, Key was to design and provide the refrigeration equipment for the Minot and Omaha projects in accordance with the specifications set out in the contracts between FSA and CEC. As relevant here, Key was to provide a Hill-Phoenix Para-Temp Rack System (Rack System) and associated equipment at each location.

Hill-Phoenix provided a 1-year limited express warranty under which each Rack System was "WARRANTED TO BE FREE FROM DEFECTS IN MATERIAL AND WORKMANSHIP . . . FOR A PERIOD OF ONE YEAR." Hill-Phoenix also provided a 4-year extended warranty on compressors. In turn, Key extended the "manufacturer's One (1) year warranty against defects in material and workmanship in parts . . . to the owner."

FSA experienced failures of the refrigeration equipment almost immediately upon installation. The cause, nature, and severity of the failures in the Minot system are matters of dispute between the parties. It is clear, however, that for the next few years, CEC, Hill-Phoenix, and Key made repeated attempts to remedy the problems and provide FSA with a properly functioning refrigeration system.

On May 23, 1995, John Vana, the vice president of engineering of Hill-Phoenix, wrote a memorandum to CEC and others. In it, Hill-Phoenix promised to warrant the unit in Minot "for parts for one year with a four year extended warranty on the compressors to be honored," after certain changes were made to the Rack System. When asked in his deposition if Hill-Phoenix was extending a new warranty, Vana stated, "After the work was done we were going to warrant it as if it shipped from the factory," and that it was his "intent to extend the warranty for a year . . . from the time all changes were made." CEC contends that within 3 months after receipt of this memorandum, it had completed the changes requested by Hill-Phoenix.

The problems in Minot continued, and in a letter dated February 27, 1996, Hamid Shekarbakht, an employee of Hill-Phoenix, advised Gary Guesman, the president of CEC, that Hill-Phoenix would no longer participate in further attempts to resolve existing or future problems with the Rack System.

On July 16, 1998, CEC sued Hill-Phoenix and Key for breach of contract and breach of warranty based on the problems at the projects in Minot and Omaha. In general, CEC alleged that the refrigeration systems in Minot and Omaha repeatedly malfunctioned. More specifically, CEC alleged that the Hill-Phoenix Rack Systems were defective and that Key and Hill-Phoenix failed to fix the refrigeration systems.

Hill-Phoenix moved for summary judgment on January 19, 1999. By order dated June 1, 1999, the district court found there was no written contract between Hill-Phoenix and CEC, and granted summary judgment for Hill-Phoenix on CEC's contract claim. By the same order, the court found there was a genuine issue of material fact as to whether Hill-Phoenix breached its express limited warranty and the implied warranties of merchantability and fitness for a particular purpose. CEC is not appealing any part of this order.

On August 23, 2000, Hill-Phoenix filed a second motion for summary judgment. The court granted summary judgment for Hill-Phoenix on claims arising out of the Minot project, finding the statute of limitations had run on the warranty claims. The court denied Hill-Phoenix's motion for summary judgment on claims arising out of the Omaha project, finding material issues of fact remained as to whether CEC gave sufficient notice of the breach to Hill-Phoenix.

Key moved for summary judgment on December 13, 2001. The court granted Key's motion for summary judgment in part, finding CEC's causes of action arising out of the Minot project were barred by the statute of limitations. The court denied Key's motion for summary judgment on claims arising out of the Omaha project. On June 24, 2002, the court, finding no just reason to delay entry of a final judgment for some of the disputed claims, issued a final order pursuant to Neb. Rev. Stat. § 25-1315(1) (Cum. Supp. 2000) on all of CEC's claims relating...

1 cases
Document | Nebraska Supreme Court – 2003
State ex rel. Counsel for Dis. v. Lechner
"..."

Try vLex and Vincent AI for free

Start a free trial

Experience vLex's unparalleled legal AI

Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
1 cases
Document | Nebraska Supreme Court – 2003
State ex rel. Counsel for Dis. v. Lechner
"..."

Try vLex and Vincent AI for free

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex