Sign Up for Vincent AI
Denbury Onshore, LLC v. APMTG Helium LLC
Representing Appellant: Darin B. Scheer, James R. Belcher, and Casey R. Terrell of Crowley Fleck PLLP, Casper, Wyoming. Argument by Mr. Scheer.
Representing Appellee: Scott P. Klosterman and Amy M. Iberlin of Williams, Porter, Day, and Neville, P.C., Casper, Wyoming; Jason A. Neville of the Spence Law Firm, LLC, Casper, Wyoming. Argument by Mr. Neville.
Before DAVIS, C.J., and FOX, KAUTZ, GRAY, JJ, and FENN, DJ.
[¶1] Denbury Onshore, LLC (Denbury), a subsidiary of Denbury Resources Inc., agreed to deliver certain amounts of helium to APMTG Helium LLC (APMTG) each year. Denbury failed to deliver the agreed-upon amounts but claimed its nonperformance was excused by two force majeure events—the failure of its contractor to complete its natural gas processing plant and the ongoing failure of its supply wells due to sulfur deposition plugging the wellbores. After a bench trial, the district court found Denbury had failed to show its non-performance was excused by a force majeure event except for a period of 36 days. It awarded APMTG over $35 million in damages and interest. Denbury appealed. We affirm.
[¶2] We restate and reorder Denbury's issues as follows:
[¶3] On January 30, 2009, APMTG, a joint venture between Air Products and Chemicals, Inc. (Air Products) and Matheson Tri-Gas, Inc. (Matheson), entered into a Helium Feedgas Agreement (HFA I) with Cimarex Energy Co. (Cimarex) and Riley Ridge, LLC (Riley Ridge). Under the agreement, Cimarex and Riley Ridge agreed to design, construct, and operate a natural gas processing plant (the Riley Ridge Plant or Plant) and to annually deliver specified quantities of helium to APMTG.1 APMTG, in turn, agreed to design, construct and operate its own gas processing plant and to purchase the specified quantities of helium from Cimarex and Riley Ridge. The HFA I required Cimarex and Riley Ridge to deliver 200 million standard cubic feet (MMscf) of helium to APMTG the first and second years of the contract and 400 MMscf per year thereafter. Cimarex and Riley Ridge agreed to expand the Riley Ridge Plant on or before the start of the third year in order to meet their increased obligations. If they failed to deliver the required quantities in any given year, they were to pay APMTG liquidated damages pursuant to a designated formula. The liquidated damages were capped at $8 million per year, and total liquidated damages for the life of the contract could not exceed APMTG's final investment to construct its plant, which APMTG predicted would be $38.6-$42.9 million.
[¶4] The HFA I "estimated" that Cimarex and Riley Ridge would begin delivering helium to APMTG on December 1, 2010, but required delivery to begin no later than December 1, 2011, absent "delays caused by any Force Majeure" or unless the parties otherwise agreed in writing. The life of the agreement was 20 years.
(Emphasis added). Section 17.3 of the HFA I required the party "whose performance under this Agreement is affected by Force Majeure [to] promptly Notify the other Party of the occurrence, and the effect and likely duration of the Force Majeure event, and ... keep the other Party informed of any changes to those circumstances." Section 17.4 required the party claiming force majeure to "as soon as practicable after the commencement of the Force Majeure, proceed with diligence and do all things reasonably practicable at its own cost to overcome and/or remedy the situation, and to recommence performance of its obligations, provided that ... neither Party shall be required to incur any extraordinary costs or make more than commercially reasonable investments."
[¶6] Cimarex was the majority owner and operator of the Riley Ridge Plant project; Riley Ridge owned only a minority interest in the project. As operator, Cimarex made the day-to-day decisions about how to run the project. It hired BCCK Engineering Incorporated (BCCK) pursuant to a turn-key contract to engineer, design and construct the Riley Ridge Plant in Big Piney, Wyoming, and bring it to "mechanical completion," which was expected to occur by December 2011.
[¶7] In July 2010, Denbury purchased Riley Ridge's interests in the Riley Ridge Plant and assumed all of its rights and obligations under the HFA I. About a year later, in June 2011, Denbury acquired Cimarex's interests in the Plant and the HFA I, as well as Cimarex's rights and obligations under the construction contract with BCCK. Two months later, on August 1, 2011, Denbury officially took over as operator of the Riley Ridge Plant project from Cimarex, which meant it began making the day-to-day decisions about how to run the Plant and Cimarex's employees became Denbury's employees. At that time, BCCK had completed the engineering design of the Riley Ridge Plant and was in the process of constructing the Plant.
[¶8] The next month, Denbury notified APMTG it was "experiencing delays in the construction and commissioning of [the Riley Ridge Plant]" and estimated it would begin delivering helium on November 15, 2011. However, that did not occur. In January 2012, after discovering BCCK had not performed in accordance with industry standards, Denbury removed BCCK from the Riley Ridge Plant project and began using its own personnel and contractors to correct BCCK's deficiencies and complete the Plant.
[¶9] On November 12, 2012, Denbury sent a letter to APMTG declaring force majeure under Article 17 of the HFA I due to "delay(s) or failure of performance of contractor(s) (of any tier) or vendor(s)" (hereinafter referred to as Contractor Failure FM). Denbury explained:
APMTG disagreed with Denbury's declaration of force majeure and sent Denbury an invoice for $8 million based on Denbury's failure to deliver the agreed-upon amounts of helium the first year of the HFA I.
[¶10] After a series of negotiations, APMTG and Denbury entered into a "Memorandum of Understanding" (MOU) on April 25, 2013. Under the terms of the MOU, the parties agreed to execute an amended helium feedgas agreement, and Denbury agreed to pay APMTG an $8 million lump sum payment and $1.1 million for APMTG's...
Try vLex and Vincent AI for free
Start a free trialTry vLex and Vincent AI for free
Start a free trialExperience vLex's unparalleled legal AI
Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Try vLex and Vincent AI for free
Start a free trialStart Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Try vLex and Vincent AI for free
Start a free trialStart Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting