Case Law Forbes v. Prime Gen. Contractors, Inc.

Forbes v. Prime Gen. Contractors, Inc.

Document Cited Authorities (12) Cited in (12) Related

P. Brandon Perkins and E. Carson Lange of Rogers Towers P.A., Fort Lauderdale, for Appellants.

No appearance for Appellee.

SALARIO, Judge.

This is an appeal from a final judgment on a claim for breach of contract. James and Fay Forbes sued Prime General Contractors, Inc. for breach after Prime walked off a home construction job. The Forbeses sought damages that included payments they made to Prime under the contract, payments they made for updated architectural plans, certain other expenses, and a loss of equity in their home. After a bench trial, the trial court found that Prime had materially breached its contract with the Forbeses but declined to award these three items of damage. We reverse the damage award in the final judgment and remand with instructions to award the Forbeses such damages as will restore them to the position they enjoyed right before they inked their contract with Prime. We affirm the judgment in all other respects.

The Forbeses and Prime signed a written contract under which Prime agreed to renovate the Forbeses' home in accord with plans drawn up by an architect. In exchange, the Forbeses agreed to pay Prime a total of $276,000 in five separate draws. Under the draw schedule, the Forbeses were to pay (a) 25% of the contract price upon signing, (b) 25% upon completion of demolition, (c) 25% upon completion of the "dry-in" stage of construction,1 (d) 15% after roofing and siding installation, and (e) the remaining 10% upon completion of the job. The contract provided that "any alteration or deviation from this agreement must be made in writing and signed by the Parties." Prime began the job as agreed, and the Forbeses paid the first two contract draws—totaling $138,000. They also paid an additional $6000 for updated architectural plans.

Under the contract, the Forbeses should not have had to pay anything more until the dry-in phase of the project was done. Unfortunately, things hit a snag before then. Prime said that the cost of the materials it needed to do the job had gone up. It told the Forbeses that the work would now cost at least $550,000—almost twice the original contract price—and demanded that the Forbeses immediately pay the third draw plus an additional $31,450 for work Prime had already done and for which the Forbeses had already paid.

Prime presented the Forbeses with a written change order making these adjustments. The Forbeses refused to sign it and told Prime that they were prepared to move forward at the contract price. Prime refused and walked off the job, leaving the Forbeses' home unfinished and uninhabitable.

Because they could not live in their home, the Forbeses began renting a house nearby so that they had somewhere to stay. In the meantime, they looked for another contractor to finish the work on their home—ultimately talking with five potential candidates to perform the service—but none was willing to handle the job. After five months of living in a rental with no luck getting the work on their house finished, the Forbeses bought a new house and moved into it. They were unable, however, to pay a mortgage on their new house and another mortgage on the home that Prime left uninhabitable. So they let the uninhabitable home go into foreclosure. At the time they contracted with Prime, the Forbeses had about $45,000 in equity in the house. That equity was lost in the foreclosure.

The Forbeses sued Prime for breach of contract, and the case went to a bench trial at which the evidence was consistent with the facts related above. The Forbeses argued that Prime materially breached the contract by demanding payments to which it was not entitled under the contract and thereafter walking off the job. Prime contended, among other things, that the Forbeses also failed to perform under the contract, to which the Forbeses answered that they were entitled to suspend performance due to Prime's material breach. The Forbeses requested the following items of damages: $138,000 in payments made pursuant to their contract with Prime, $6000 for updated architectural plans, $45,000 of lost equity in their home, $5600 in rent, and various other expenses incurred in reliance on their contract with Prime. It is clear from the damages the Forbeses requested that they were asking to be put in the position they would have occupied had they not contracted with Prime in the first place. Prime asserted and litigated at trial an affirmative defense that the Forbeses failed to mitigate their damages.

About a month after the bench trial wrapped, the trial court entered a final judgment. It found that Prime had materially breached the contract as the Forbeses argued. However, it awarded the Forbeses as damages only the $5600 in rent they paid while searching for a new contractor. The trial court explained that "[t]he purpose of contract damages is to put the injured party in as good a position as that in which full performance would have put him" and concluded that the Forbeses

failed to offer persuasive or credible evidence at trial of the difference between the market value of the home had it been completed, less such part of the contract price that has not been paid, and the value of the construction that has been furnished by [Prime] thus far.

The court also found, without elaboration, that the Forbeses "made a financial decision not to engage in reasonable mitigation efforts" with respect to their damages.

This is the Forbeses' timely appeal of the final judgment. They argue two points: (1) by looking to place them in the position they would have occupied had Prime fully performed instead of the position they would have occupied had they never contracted with Prime, the trial court used an incorrect method of calculating damages; and (2) the trial court's finding that the Forbeses failed to mitigate their damages is unsupported by the evidence. We review the first point de novo, see Tubby's Customs, Inc. v. Euler, 225 So.3d 405, 407 (Fla. 2d DCA 2017), and the second for competent substantial evidence, cf. RNK Family Ltd. P'ship v. Alexander-Mitchell Assocs., 890 So.2d 297, 299 (Fla. 2d DCA 2004). See also Craigside, LLC v. GDC View, LLC, 74 So.3d 1087, 1089 (Fla. 1st DCA 2011) ("While the parties are entitled to de novo review of the trial court's rulings with respect to the legal effect of the contract, we are bound by the trial court's findings of fact in a case, like the present one, where competent, substantial evidence supports the findings."). Both points have merit.

Method of calculating damages. In calculating damages, the trial court erred by failing to honor the Forbeses' choice to deem the contract totally breached and recover those damages that would restore them to the position they occupied immediately before contracting with Prime. When one party to a contract commits a material breach, the nonbreaching party has the option to treat the breach "as a breach of the entire contract—in other words, an entire or total breach."2 Hyman v. Cohen, 73 So.2d 393, 397 (Fla. 1954) (quoting 12 Am. Jur. Contracts § 389 ); see also 24 Richard A. Lord, Williston on Contracts § 64:27 (4th ed. 2018). From the perspective of the nonbreaching party, there are two main consequences of that decision: (1) the nonbreaching party may suspend his or her own performance of the contract, see Rector v. Larson's Marine, Inc., 479 So.2d 783, 785 (Fla. 2d DCA 1985), and (2) the nonbreaching party can elect one of two damage remedies in a suit for breach, see City of Miami Beach v. Carner, 579 So.2d 248, 251 (Fla. 3d DCA 1991).

When a party seeks damages for a total breach, "[h]e may treat the contract as void and seek the damages that will restore him to the position he was in immediately prior to entering the contract." Rector, 479 So.2d at 785 ; see also McCray v. Murray, 423 So.2d 559, 561 (Fla. 1st DCA 1982). Or, in the alternative, he may instead "affirm the contract, ‘insist upon the benefit of his bargain, and seek the damages that would place him in the position he would have been in had the contract been completely performed.’ " Tubby's Customs, 225 So.3d at 407 (quoting Citizen's Prop. Ins. Corp. v. Amat, 198 So.3d 730, 734 (Fla. 2d DCA 2016) ). In the case of a breached...

5 cases
Document | U.S. Court of Appeals — Eleventh Circuit – 2019
Benkovitch v. Vill. of Key Biscayne
".... . . relieves the injured party from further performance of its contractual duties"); see also Forbes v. Prime Gen. Contractors, Inc., 255 So. 3d 448, 451 (Fla. Dist. Ct. App. 2018) (stating that the nonbreaching party has the option to "treat the contract as void" (citation omitted)). Tha..."
Document | U.S. District Court — District of Hawaii – 2019
United States v. David Boland, Inc.
"...breach," the nonbreaching party has the option to treat the breach as "an entire or total breach." Forbes v. Prime Gen. Contrs., Inc., 255 So. 3d 448, 451 (Fla. 2d Dist. Ct. App. 2018) (quoting Hyman v. Cohen, 73 So. 2d 393, 397 (Fla. 1954)). "[T]here are two main consequences of that decis..."
Document | Florida District Court of Appeals – 2021
Cano, Inc. v. Judet
"...may seek the benefit of his bargain. See McCray v. Murray , 423 So. 2d 559, 561 (Fla. 1st DCA 1982). Forbes v. Prime General Contractors, Inc. , 255 So. 3d 448 (Fla. 2d DCA 2018), explains the alternative measures of damages in a construction contract case. In that case, the homeowners, the..."
Document | U.S. Bankruptcy Court — Northern District of Florida – 2021
In re Manown Eng'g Co.
"..., 985 So. 2d 56, 58 (Fla. 4th DCA 2008) ).41 In re Jeffrey L. Miller Invs., Inc. , 610 B.R. at 704.42 Forbes v. Prime Gen. Contractors, Inc. , 255 So. 3d 448, 451 (Fla. 2d DCA 2018) (quoting Hyman v. Cohen , 73 So. 2d 393, 397 (Fla. 1954) ).43 Id. (quoting Rector v. Larson's Marine, Inc. , ..."
Document | Florida District Court of Appeals – 2020
Cuomo Trading, Inc. v. World Contract S.R.L.
"...this case, we do not quarrel with the trial court's legal conclusion and affirm the final judgment. See Forbes v. Prime Gen. Contractors, Inc., 255 So. 3d 448, 451 (Fla. 2d DCA 2018) (providing that, when faced with a breach of contract, the non-breaching party may treat the contract as voi..."

Try vLex and Vincent AI for free

Start a free trial

Experience vLex's unparalleled legal AI

Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
5 cases
Document | U.S. Court of Appeals — Eleventh Circuit – 2019
Benkovitch v. Vill. of Key Biscayne
".... . . relieves the injured party from further performance of its contractual duties"); see also Forbes v. Prime Gen. Contractors, Inc., 255 So. 3d 448, 451 (Fla. Dist. Ct. App. 2018) (stating that the nonbreaching party has the option to "treat the contract as void" (citation omitted)). Tha..."
Document | U.S. District Court — District of Hawaii – 2019
United States v. David Boland, Inc.
"...breach," the nonbreaching party has the option to treat the breach as "an entire or total breach." Forbes v. Prime Gen. Contrs., Inc., 255 So. 3d 448, 451 (Fla. 2d Dist. Ct. App. 2018) (quoting Hyman v. Cohen, 73 So. 2d 393, 397 (Fla. 1954)). "[T]here are two main consequences of that decis..."
Document | Florida District Court of Appeals – 2021
Cano, Inc. v. Judet
"...may seek the benefit of his bargain. See McCray v. Murray , 423 So. 2d 559, 561 (Fla. 1st DCA 1982). Forbes v. Prime General Contractors, Inc. , 255 So. 3d 448 (Fla. 2d DCA 2018), explains the alternative measures of damages in a construction contract case. In that case, the homeowners, the..."
Document | U.S. Bankruptcy Court — Northern District of Florida – 2021
In re Manown Eng'g Co.
"..., 985 So. 2d 56, 58 (Fla. 4th DCA 2008) ).41 In re Jeffrey L. Miller Invs., Inc. , 610 B.R. at 704.42 Forbes v. Prime Gen. Contractors, Inc. , 255 So. 3d 448, 451 (Fla. 2d DCA 2018) (quoting Hyman v. Cohen , 73 So. 2d 393, 397 (Fla. 1954) ).43 Id. (quoting Rector v. Larson's Marine, Inc. , ..."
Document | Florida District Court of Appeals – 2020
Cuomo Trading, Inc. v. World Contract S.R.L.
"...this case, we do not quarrel with the trial court's legal conclusion and affirm the final judgment. See Forbes v. Prime Gen. Contractors, Inc., 255 So. 3d 448, 451 (Fla. 2d DCA 2018) (providing that, when faced with a breach of contract, the non-breaching party may treat the contract as voi..."

Try vLex and Vincent AI for free

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex