Case Law Golden Rule Farms, Inc. v. Or. Water Res. Dep't

Golden Rule Farms, Inc. v. Or. Water Res. Dep't

Document Cited Authorities (6) Cited in (3) Related

Sara Kobak, Portland, argued the cause for petitioner. Also on the briefs were Elizabeth E. Howard, Shonee Langford, and Schwabe, Williamson & Wyatt, P.C., Portland.

Inge D. Wells, Assistant Attorney General, Eugene, argued the cause for respondent. Also on the brief were Ellen F. Rosenblum, Attorney General, and Benjamin Gutman, Solicitor General, Salem.

Lisa A. Brown filed the brief amicus curiae for WaterWatch of Oregon.

Before Ortega, Presiding Judge, and Lagesen, Chief Judge, and Powers, Judge.

LAGESEN, C. J.

Petitioner holds multiple groundwater permits in Harney County. This case involves two of those permits. When petitioner failed to complete construction of the wells authorized by the relevant permits or apply the water to beneficial use by the deadlines specified in the permits, petitioner applied for extensions under ORS 537.630 and OAR 690-315-0040. The Oregon Water Resources Department (OWRD) issued final orders denying those extensions and petitioner initiated this judicial review proceeding under ORS 183.482. After petitioner initiated this proceeding, OWRD withdrew its final orders under ORS 183.482(6), and then issued orders on reconsideration in which it modified several findings of fact. We affirm because petitioner failed to exhaust administrative remedies and to the extent petitioner challenges the modified findings on reconsideration, those challenges fail.

The relevant facts are mostly procedural and not disputed. Any substantive facts are drawn from the uncontested factual findings in the orders on review. Klein v. B.O.L.I. , 317 Or App 138, 506 P.3d 1108, rev den , 369 Or. 705, 509 P.3d 119 (2022).

As noted, this case involves two groundwater permits: G-17441 and G-17100. Both are for groundwater within the Greater Harney Valley Groundwater Area of Concern (GHVGAC). OWRD issued Permit G-17441 in 2015, authorizing "the use of up to 2.0 cfs of water from three wells in Malheur Lake Basin for irrigation use on 160 acres." The permit superseded a prior permit for which construction had not been completed. When G-17441 was issued, the completion date for construction and application of water was October 1, 2018. Permit G-17100 had a similar trajectory. OWRD issued G-17100 on October 31, 2013. It authorized the use of up to 4 cfs of water from two wells in Malheur Lake Basin for irrigation of 320 acres. It specified a completion date for construction and "complete application of water" by October 31, 2018. Between the dates the permits issued and the specified completion dates, no action was taken to begin construction on the wells authorized by the permits.

In March 2017, petitioner submitted Permit Amendment T-12609 to OWRD. That application sought to amend both permits at issue in this case. With respect to both, it sought to change the place of use and places of appropriation authorized under the permits to other locations within the GHVGAC. In September 2018, OWRD notified petitioner by letter that it could not process the application "without an active completion date" for Permits G-17441 and G-17100. It advised that petitioner needed to seek—and obtain—approval of extensions of time for those permits for OWRD to approve the amendment application. OWRD did not receive a response to its September letter and denied the amendment application on November 7, 2018, on the ground that petitioner was "unable to complete the application of the water to beneficial use" as required under the permits and "[w]ithout current dates for complete application of water," OWRD could not approve the amendment.

On November 19, 2018, petitioner submitted the extension requests at issue in this case, seeking to extend the completion dates of both permits to October 1, 2019. After a notice-and-comment period, OWRD issued proposed final orders denying both requested extensions in April 2019. The proposed final orders advised that petitioner was entitled to protest the denials as allowed under OAR 690-315-0100 and OAR 690-315-0060 by filing a written protest with OWRD by May 31, 2019. Petitioner did not protest either proposed final order and, on June 14, 2019, OWRD issued final orders denying each extension. In the final orders, as it had in the proposed final orders, OWRD determined that "[t]he applicant has not demonstrated good cause for the permit extension pursuant to ORS 537.630, 539.010(5) and OAR 690-315-0040(2)."

Almost two months later, petitioner petitioned OWRD to reconsider its final orders. It asserted that OWRD "did not act in good faith or in a timely manner during the review process" of permit amendment T-12609 and that, but for OWRD's alleged failure to act in good faith, petitioner would not have required extensions. OWRD did not act on the petition, and it was deemed denied by operation of law. ORS 183.482(1).

Petitioner sought judicial review. After petitioner filed its opening brief, OWRD withdrew the final orders for reconsideration under ORS 183.482(6) and filed orders on reconsideration that modified several factual findings but otherwise adhered to the original orders denying the extensions. Petitioner then filed a supplemental brief, in which it challenged several of the modified findings.

On review, petitioner argues that, in determining that it did not demonstrate "good cause" for the permit extensions, OWRD "acted contrary to statute and outside of the range of its permissible discretion." Petitioner contends that OWRD should not have considered its failure to complete construction of the wells authorized by the permits because petitioner "sought the extensions solely to apply the groundwater to beneficial use under the permits," and was not seeking to build the wells. Petitioner also argues that OWRD erred when it did not take into account "its own unexplained 14-month delay in processing" the permit amendments requested in T-12609, pointing to the requirement in ORS 537.630(2) that OWRD must consider the extent to which "other governmental requirements relating to the project have significantly delayed completion of construction or perfection of the right." ORS 537.630(2). Finally, petitioner asserts that various factual findings, including some of the modified findings included in OWRD's orders on reconsideration, are not supported by substantial evidence.

OWRD responds that petitioner's contentions are not reviewable because petitioner did not exhaust administrative remedies by employing the protest procedure, and also because petitioner did not preserve the issues by raising them with OWRD in the first instance. OWRD otherwise argues that its order reflects a...

4 cases
Document | Oregon Court of Appeals – 2023
Watson v. Bd. of Parole & Post-Prison Supervision
"...goes without saying that for an administrative remedy to be ‘exhaustible’ it must be available."); Golden Rule Farms v. Water Resources Dept. , 321 Or App 43, 48, 515 P.3d 908 (2022) (explaining that a person generally must present an issue to the agency before it will be considered on judi..."
Document | Oregon Court of Appeals – 2023
Sohappy v. Bd. of Parole & Post-Prison Supervision
"...interpretation of OAR 255-085-0020(1) as reflected in its order setting his SONL at Level 2. See Golden Rule Farms v. Water Resources Dept. , 321 Or App 43, 48, 515 P.3d 908 (2022) (generally, when "an agency provides a process for raising issues to it, the doctrine [of administrative exhau..."
Document | Oregon Court of Appeals – 2022
Gould v. Deschutes Cnty., A178949
"...We reject petitioner's contention, in a memorandum of supplemental authority, that our recent opinion in Golden Rule Farms v. Water Resource Dept. , 321 Or App 43, 515 P.3d 908 (2022), somehow supports its argument that the pendency of the challenge to Permit G-17036 has some bearing on Tho..."
Document | Oregon Court of Appeals – 2022
K. R. M. v. Baker
"..."

Try vLex and Vincent AI for free

Start a free trial

Experience vLex's unparalleled legal AI

Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
4 cases
Document | Oregon Court of Appeals – 2023
Watson v. Bd. of Parole & Post-Prison Supervision
"...goes without saying that for an administrative remedy to be ‘exhaustible’ it must be available."); Golden Rule Farms v. Water Resources Dept. , 321 Or App 43, 48, 515 P.3d 908 (2022) (explaining that a person generally must present an issue to the agency before it will be considered on judi..."
Document | Oregon Court of Appeals – 2023
Sohappy v. Bd. of Parole & Post-Prison Supervision
"...interpretation of OAR 255-085-0020(1) as reflected in its order setting his SONL at Level 2. See Golden Rule Farms v. Water Resources Dept. , 321 Or App 43, 48, 515 P.3d 908 (2022) (generally, when "an agency provides a process for raising issues to it, the doctrine [of administrative exhau..."
Document | Oregon Court of Appeals – 2022
Gould v. Deschutes Cnty., A178949
"...We reject petitioner's contention, in a memorandum of supplemental authority, that our recent opinion in Golden Rule Farms v. Water Resource Dept. , 321 Or App 43, 515 P.3d 908 (2022), somehow supports its argument that the pendency of the challenge to Permit G-17036 has some bearing on Tho..."
Document | Oregon Court of Appeals – 2022
K. R. M. v. Baker
"..."

Try vLex and Vincent AI for free

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex