By R. Lee Vail, P.E., Ph.D.
At the very end of 2016, the Fifth Circuit Court of Appeals vacated two Occupational Safety and Health Administration (“OSHA”) citations for alleged violations of Process Safety Management (“PSM”) regulations. In that case, the Court held that OSHA was barred from issuing a citation for the failure to act on Process Hazard Analysis (“PHA”) findings/recommendations that remained open beyond the six month statute of limitations provided in 29 U.S.C.A. §658(c) of the Occupational Safety Health Act of 1970. See, Delek Ref., Ltd. v. Occupational Safety & Health Review Comm’n, 845 F.3d 170, 179 (5th Cir. 2016).
Conversely, violations of the Clean Air Act are recognized to be subject to the general federal five-year statute of limitations established by 28 U.S.C. § 2462. See Nat’l Parks & Conservation Ass’n, Inc. v. Tennessee Valley Auth., 502 F.3d 1316, 1322 (11th Cir. 2007). Consistent with this, the “duration of violation” factor under the Environmental Protection Agency (“EPA”) “Combined Enforcement Policy for Clean Air Act Sections 112(r)(1), 112(r)(7) and 40 C.F.R. Part 68 ” reaches its maximum at 60 months. At first glance, it would appear that the Delek decision might have little or no impact on RMP penalties, but that would be incorrect.
Some...