Case Law Tower Access Grp., LLC v. S. Union Twp. Zoning Hearing Bd.

Tower Access Grp., LLC v. S. Union Twp. Zoning Hearing Bd.

Document Cited Authorities (9) Cited in (6) Related

Richard M. Williams, Kingston, for appellant.

Simon B. John, Uniontown, for appellee.

BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge, HONORABLE PATRICIA A. McCULLOUGH, Judge, HONORABLE CHRISTINE FIZZANO CANNON, Judge

OPINION BY JUDGE McCULLOUGH

Tower Access Group, LLC (TAG) appeals from the September 22, 2017 order of the Court of Common Pleas of Fayette County (trial court) affirming the decision of the South Union Township Zoning Hearing Board (Board), which denied TAG's application for a special exception to build a communication tower in South Union Township (Township).

Facts and Procedural History

The underlying facts are not in dispute and are garnered from the Board's decision, the trial court's original opinion and order dated September 22, 2017, as well as the trial court's Pa.R.A.P. 1925 opinion filed on December 15, 2017. On May 16, 2016, TAG applied for, and was granted, a zoning certificate to build a communication tower in a wooded area off 1 Grace Lane in the Township on property owned by Grace Brethren Church of Uniontown. Specifically, TAG sought to lease 10,000 square feet of this property from the church to build a 180-foot monopole tower which would have an overall height of 188 feet. Once constructed, Verizon Wireless intended to install its antennas and equipment on the tower, including a 12-foot by 20-foot platform with a canopy and equipment cabinets. TAG would access the tower via a proposed gravel access road through the woods on the property and there would be a parking area nearby for service technicians. The initial construction of the tower was expected to last four to six weeks, after which the service technicians would visit the tower approximately once per month. TAG chose the particular location for the tower in order to improve cellular coverage in the area.

However, the Township's Board of Supervisors subsequently revoked TAG's zoning certificate on July 27, 2016, noting that the proposed site for the tower was located in an R-1 Zone, which is reserved for residences and establishments that provide services to the community. Other types of construction in an R-1 Zone, such as public service facilities, are permitted by special exception. The Board of Supervisors determined that TAG's tower constituted a public service facility. TAG thereafter filed an application with the Board seeking to appeal the action by the Board of Supervisors and, alternatively, seeking a special exception for the tower.

Board's Public Hearing

The Board conducted a public hearing with respect to TAG's application on December 15, 2016. At this hearing, the Township first presented the testimony of John Over Jr., the Township's engineer. After complaints by residents, the Township's Board of Supervisors requested that Over review TAG's original application and the zoning certificate that was issued based upon this application. Upon completion of this review, Over sent a letter to TAG dated July 27, 2016, revoking the zoning certificate based upon his determination that the proposed tower use was not defined in the South Union Township Zoning Ordinance (Ordinance)1 and was most similar to a public service facility, which is only permitted by special exception in an R-1 Zone. Over noted that at his request, Joseph Burke, the Township's Zoning Officer, sent an identical letter to TAG that same day. (Reproduced Record (R.R.) at 19a-24a.)

On cross-examination, Over explained that the decision to revoke the zoning certificate originated with complaints from Township residents to the Board of Supervisors with respect to the issuance of the certificate and no posting of the property. Over could not cite to any specific provision of the Ordinance that authorizes the Board of Supervisors to conduct an administrative review when a use is neither permitted nor prohibited in the Ordinance, although he testified that such a provision existed in both the Ordinance and the Municipalities Planning Code (MPC).2 (R.R. at 25a-31a.)

TAG then presented the testimony of Matthew Smith, a professional civil engineer and owner of Red Swing Consulting Services, the company that prepared the plans attached to TAG's original application for a zoning certificate filed with the Township. Smith described the area around the proposed tower as a wooded area in between a shopping center and country club, with an elementary school to the south and residential properties to the north. He described the condition of the property as heavily wooded. He noted that the plans call for a 50-foot by 70-foot gravel compound area, to be accessed by a gravel road, and a 180-foot steel monopole placed in the center of the compound area with an 8-foot lightning rod on top. (R.R. at 35a-39a.)

He did not anticipate any traffic concerns resulting from the site, stating that, after the initial construction time of four to six weeks, service technicians would visit the site maybe once a month. He also noted that the plans called for a 12-foot by 20-foot equipment platform on a concrete pad with three outdoor cabinets each about the size of a refrigerator and that the compound area would be secured by a locked gate and a six-foot-high wood slat fence that would also assist in concealing the equipment. With regard to setbacks, Smith testified that the site was irregularly shaped, similar to an arrowhead, and would be located 40 feet from the western property line, 800 feet from the northern property line, and 1,200 feet from the eastern property line. He also stated that the site was 339 feet from Foreman Avenue, the closest public right-of-way. (R.R. at 40a-43a.)

On cross-examination, Smith acknowledged that neither he nor his company prepared TAG's original application for a zoning certificate, only the plans attached to the same. He indicated that the exact width of the base of the tower was determined by a structural engineer based on many factors, including wind load, snow load, and other geotechnical conditions. He also indicated that the optimal height of the tower was determined by a radio frequency engineer. He admitted that he did not visit the proposed site prior to submission of the plans but that another representative visited and conducted a survey of the entire church property. He stated that Verizon Wireless will be the sole user of the tower once erected but that there was room for other carriers. Additionally, Smith testified that the leased site consisted of 10,000 square feet and would include an access easement for the proposed gravel road, which would be 12 feet wide. (R.R. at 45a-62a.)

TAG next presented the testimony of Shreyas Patel, a radio frequency/wireless engineer for Verizon Wireless. He explained that Verizon Wireless sought to improve in-building coverage, both residential and commercial, in the area of the proposed tower. He identified a color-coded map that he prepared for the benefit of the Board identifying the areas of in-building coverage in and around the Township and the desired areas where Verizon Wireless sought to improve this coverage via installation of the tower. He noted that improving in-building coverage, especially with respect to commercial buildings constructed of steel and concrete, requires a stronger signal. He included a map that showed the areas that would be reached by the new tower, which he said would definitely improve the in-building coverage in those areas. (R.R. at 64a-73a.)

On cross-examination, Patel admitted that he did not visit the area but stated that a site acquisition person actually investigated the proposed location. He identified the tan or yellow shaded areas of his color-coded map as those where indoor wireless coverage was weak or unreliable. He noted that such areas were determined by measuring signal strength. However, he acknowledged that the maps he provided extended beyond the limits of the Township. He also acknowledged that ground elevation is an important consideration for placement of a tower, such as when dealing with a low-lying valley area, which would require a higher tower. He noted that he did visit the proposed location about a month before the December 15, 2016 hearing and did not observe any obstructions in the area that would impact the coverage to be provided by the new tower. He described his general role as advising the individual responsible for site acquisition regarding areas where a tower would be beneficial and then reviewing any potential sites. Patel further admitted that he had no statistics or information with him regarding complaints about coverage in the area from Verizon Wireless users. He characterized the proposed location of the new tower as the ideal location that would provide good coverage for the area. (R.R. at 73a-90a.)

On re-direct examination, Patel explained that Verizon Wireless needed increased coverage and capacity in the area, the latter representing the maximum number of calls or data transmissions a tower can handle. (R.R. at 91a-92a.)

TAG next presented the testimony of Scott Devlin of Unified Business Technologies, Inc., who was hired by Verizon Wireless as a site acquisition/real estate consultant. He testified that Verizon Wireless had negotiated a lease agreement with Grace Brethren Church of Uniontown, the owner of the property where the proposed tower would be located. He described how Verizon Wireless provided him with a search area request form, which identifies certain mapping coordinates where a new site is desirable. He noted that the proposed site was the primary candidate, but that he had investigated other sites within the Township. Subsequent to execution of the lease agreement, Devlin explained that TAG sought and obtained a zoning certificate for the proposed tower. He identified the July 27, 2016 letter from Over...

4 cases
Document | U.S. District Court — Middle District of Pennsylvania – 2020
Ne. Pa. SMSA LP v. Smithfield Twp. Bd. of Supervisors
"... ... 23, 2017, pursuant to the MPC and the Zoning Ordinance of the Smithfield Township, Monroe ... 27-17); (18) Pre-Hearing Statement (Doc. 27-18); (19) Existing In-Building ... 's M-1 Industrial District, a communications tower "is allowed as a conditional use." ( Id. at ¶ ... , screening on the outside and a stone access drive leading to the compound." (Doc. 27-23, at ... or services." The court in Tower Access Grp., LLC. v. S. Union Twp. Zoning Hearing Bd. , 192 ... "
Document | Pennsylvania Commonwealth Court – 2020
Heisler's Egg Farm, Inc. v. Walker Twp. Zoning Hearing Bd.
"... ... , absent a showing of a detrimental effect on the community.’ " Tower Access Grp., LLC v. S. Union Twp. Zoning Hearing Bd. , 192 A.3d 291, 300 ... "
Document | Pennsylvania Commonwealth Court – 2022
Czachowski v. Zoning Board of Adjustment of City of Pittsburgh
"... ... 21, 2019, the Zoning Board conducted a hearing on Landowner's application for a special ... exception to address parking and access. ZONING CODE § 911.04.A.57. 8 The Zoning Board ... Tower Access Group, LLC v. South Union Township Zoning ... "
Document | Pennsylvania Commonwealth Court – 2019
Siya Real Estate LLC v. Allentown City Zoning Hearing Bd.
"... ... Co., Inc. v. Zoning Hearing Bd. of Adams Twp., Cambria Cty. , 612 Pa. 598, 32 A.3d 587, 592 (2011). As ... of a detrimental effect on the community.’ " Tower Access Grp., LLC v. S. Union Twp. Zoning Hearing Bd. , 192 ... "

Try vLex and Vincent AI for free

Start a free trial

Experience vLex's unparalleled legal AI

Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
4 cases
Document | U.S. District Court — Middle District of Pennsylvania – 2020
Ne. Pa. SMSA LP v. Smithfield Twp. Bd. of Supervisors
"... ... 23, 2017, pursuant to the MPC and the Zoning Ordinance of the Smithfield Township, Monroe ... 27-17); (18) Pre-Hearing Statement (Doc. 27-18); (19) Existing In-Building ... 's M-1 Industrial District, a communications tower "is allowed as a conditional use." ( Id. at ¶ ... , screening on the outside and a stone access drive leading to the compound." (Doc. 27-23, at ... or services." The court in Tower Access Grp., LLC. v. S. Union Twp. Zoning Hearing Bd. , 192 ... "
Document | Pennsylvania Commonwealth Court – 2020
Heisler's Egg Farm, Inc. v. Walker Twp. Zoning Hearing Bd.
"... ... , absent a showing of a detrimental effect on the community.’ " Tower Access Grp., LLC v. S. Union Twp. Zoning Hearing Bd. , 192 A.3d 291, 300 ... "
Document | Pennsylvania Commonwealth Court – 2022
Czachowski v. Zoning Board of Adjustment of City of Pittsburgh
"... ... 21, 2019, the Zoning Board conducted a hearing on Landowner's application for a special ... exception to address parking and access. ZONING CODE § 911.04.A.57. 8 The Zoning Board ... Tower Access Group, LLC v. South Union Township Zoning ... "
Document | Pennsylvania Commonwealth Court – 2019
Siya Real Estate LLC v. Allentown City Zoning Hearing Bd.
"... ... Co., Inc. v. Zoning Hearing Bd. of Adams Twp., Cambria Cty. , 612 Pa. 598, 32 A.3d 587, 592 (2011). As ... of a detrimental effect on the community.’ " Tower Access Grp., LLC v. S. Union Twp. Zoning Hearing Bd. , 192 ... "

Try vLex and Vincent AI for free

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex