Sign Up for Vincent AI
Tymeless Flooring, Inc. v. Rotolo Consultants, Inc.
Wayne J. Jablonowski, Law Office of Wayne J. Jablonowski, APLC, Slidell, LA, for Plaintiff/Appellant.
John R. Walker, Bailey D. Morse, Jones, Fussell, L.L.P., Covington, LA, for Defendant/Appellee.
(Court composed of Chief Judge JAMES F. McKAY, III, Judge DANIEL L. DYSART, Judge ROSEMARY LEDET ).
This is a breach of contract suit. The narrow issue presented is whether the payment provision in the construction contract between the parties is a “pay-when-paid” clause—a term of payment—or a “pay-if-paid” clause—a suspensive condition.1 The trial court, finding that the contract contained a suspensive condition, sustained the dilatory exception of prematurity filed by the defendant, Rotolo Consultants, Inc. (“RCI”), and dismissed without prejudice the suit filed by the plaintiff, Tymeless Flooring, Inc. (“Tymeless”). From this judgment, Tymeless appeals. For the reasons that follow, we find that the contract contains a term of payment—a “pay-when-paid” clause. Accordingly, we reverse and remand.
This case arises out of a construction contract between Dryades Young Men's Christian Association (“Dryades”) and Ellis Construction, Inc. (“Ellis”), the prime contractor, for a project known as the Dryades YMCA Natatorium and Wellness Center in New Orleans, Louisiana (the “Project”). After contracting with Dryades, Ellis entered into a subcontract with RCI for certain portions of the work on the Project. RCI, in turn, entered into a subcontract with Tymeless to perform additional work, as an extra to the contract (the “Subcontract”). Tymeless was thus a subcontractor of a subcontractor on the Project.
After fully performing the work under the Subcontract, Tymeless invoiced RCI. Although RCI made a partial payment, it failed, despite amicable demand, to make full payment. On November 16, 2012, Tymeless filed a Statement of Claim and Privilege with the Orleans Parish Recorder of Mortgages in the principal amount of $24,595.00. On November 15, 2013, Tymeless commenced this suit against RCI.3 In its petition, Tymeless alleged that RCI was liable to it for the full amount of its lien claim, plus interest, attorneys' fees, and costs. In support of its claim, Tymeless cited the Subcontract; the Private Works Act, La. R.S. 9:4801, et seq; and the Open Account statute, La. R.S. 9:2781.
In response, RCI filed a dilatory exception of prematurity. The sole basis for RCI's exception was the payment provision contained in Section 5 of the Subcontract,4 which provides as follows:
Payments are to be made as follows: 90% of Sub–Contractor's approved invoices or pay request will be paid subject to the conditions following, after payment by the Owner for Sub–Contractor's work. Retention of 10% will be released upon satisfactory completion of this contract and release of final payment by the Owner.5
RCI's position was that the underlying proceeding is premature because the payment provisions contained in the contract have not been triggered. Stated otherwise, RCI's position was that the Subcontract specified that the amounts Tymeless was seeking to recover from RCI were not owed by RCI “unless and until” RCI itself was paid by Ellis. Given that Ellis had not yet paid RCI these amounts, RCI contended that Tymeless' suit to secure payment from RCI was premature.
Agreeing with RCI, the trial court granted RCI's exception of prematurity and dismissed Tymeless' suit without prejudice. Tymeless then filed a motion for new trial, which the trial court summarily denied. This appeal followed.
An exception of prematurity poses the question of “whether the cause of action has matured to the point where it is ripe for a decision by the court.”
1 Frank L. Maraist and Harry T. Lemmon, LOUISIANA CIVIL LAW TREATISE: CIVIL PROCEDURE § 6.6 (1999). An exception of prematurity is governed by La. C.C.P. art. 423, which sets forth the following pertinent rules:
In this case, the dispositive facts are not disputed. The only dispute presented is a legal one. When, as in this case, “there is no dispute as to the dispositive facts, the issue can be decided as a matter of law and the review is de novo. ” Demma v. Automobile Club Inter–Insurance Exch., 08–2810, p. 7, n. 4 (La.6 26/09), 15 So.3d 95, 100 (citing Kevin Associates, L.L.C. v. Crawford, 03–0211, p. 15 (La.1/30/04), 865 So.2d 34, 43 ).
The narrow legal issue presented in this case is whether, under the provisions of the Subcontract, the non-payment by Ellis (a primary contractor) to RCI (a subcontractor) is a suspensive condition—a “pay-if-paid” clause—to RCI's obligation to pay Tymeless (RCI's subcontractor). If so, then, as RCI contends and the trial court found, Tymeless' suit is premature. If not, then, as Tymeless contends, the provision is a term of payment—a “pay-when-paid” clause—and the trial court erred in granting the exception of prematurity and dismissing the suit.7
In order to provide a framework for addressing the issue, we first summarize the jurisprudence distinguishing two types of payment clauses commonly inserted into construction contracts—“pay-when-paid” and “pay-if-paid” clauses. “The difference between a ‘pay-when-paid’ clause and a ‘pay-if-paid’ clause is vast.” BMD Contractors, Inc. v. Fidelity and Deposit Co. of Maryland, 828 F.Supp.2d 978, 985 (S.D.Ind.2011).8
Explaining the vast difference between these two type of clauses, a commentator notes:
Ronald P. Friedberg, “PAY–IF–PAID” CONTRACT PROVISIONS, Providing Some Enforcement Consistency and Predictability in an Unsettled Area of Law, 57 No. 2 DRI For Def. 23 (2015).
A “pay-when-paid” clause is susceptible to the following two interpretations: “(1) as setting a condition precedent to payment or (2) as fixing the point in time when payment would ordinarily occur.” Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd., 196 Ohio App.3d 784, 794, 965 N.E.2d 1007, 1014 (2011). The majority view nationwide is that “pay-when-paid” clauses are timing mechanisms, not condition precedents. William M. Hill, Mary–Beth McCormack, Pay–If–Paid Clauses: Freedom of Contract or Protecting the Subcontractor from Itself?, 31 Construction Law. 26 (Winter 2011). Explaining the rationale behind the majority view, a commentator notes:
Id. at 26–27. “Courts that have enforced such [“pay-if-paid”] provisions uphold the parties' freedom to contract in such a way that those least able to control or minimize the risk are nevertheless the ones most likely to suffer the consequences of its realization.” 3 Bruner & O'Connor, CONSTRUCTION LAW § 8:47 (2014).
The seminal nationwide case on “pay-when-paid” clauses is Thos. J. Dyer Co. v. Bishop Intern. Engineering Co., 303 F.2d 655 (6th Cir.1962), which espouses the majority view outlined above. The subcontract in Dyer provided that “no part of [the subcontract price] ......
Try vLex and Vincent AI for free
Start a free trialExperience vLex's unparalleled legal AI
Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Try vLex and Vincent AI for free
Start a free trialStart Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting