Sign Up for Vincent AI
United States ex rel. Am. Civil Constr., LLC v. Hirani Eng'g & Land Surveying, P.C.
This matter is on remand from the D.C. Circuit for additional fact-finding on Plaintiff American Civil Construction, LLC's Miller Act claim against Defendant Colonial Surety Company and Colonial's statute-of-limitations defense to that claim. The Circuit directed this court "to make findings of fact as to when the Prime Contract was terminated and whether ACC performed labor or supplied material on April 29 and/or April 30." United States ex rel. Am. Civil Constr., LLC v. Hirani Eng'g & Land Surveying, PC, 962 F.3d 587, 594 (D.C. Cir. 2020) ("Hirani II"). On remand, the court invited the parties to address these issues in supplemental filings. See Pl.'s Supplemental Proposed Findings of Fact and Conclusions of Law, ECF No. 106 [hereinafter Pl.'s Suppl.]; Defs.' Supplemental Proposed Findings of Fact and Conclusions of Law, ECF No. 107 [hereinafter Defs.' Suppl.]. Having considered the parties' submissions, and the entire trial record, the court makes the following supplemental findings of fact and conclusions of law.
1. In a letter dated Friday, April 26, 2013, Contracting Officer Jerome T. Rifkin of the U.S. Army Corps of Engineers ("USACE") terminated the Prime Contract between the USACE and Hirani Engineering and Land Surveying, P.C. ("Termination Letter"). Pl.'s Ex. 150; Def.'s Ex. 77. According to the letter, the "termination [was] effective immediately." Id.
2. The Termination Letter appears twice in the trial record: Plaintiff's Exhibit 150 and Defendants' Exhibit 77. The first two pages of each exhibit are the same, consisting of the text of the correspondence. The face of the Termination Letter indicates it was sent from the USACE in Baltimore, Maryland, via "CERTIFIED MAIL-RETURN RECEIPT REQUESTED," to Jitendra Hirani, President of Hirani Engineering and Land Surveying, P.C., at Hirani's office in Jericho, New York. Defs.' Ex. 77 at 1; Pl.'s Ex. 150 at 1. The record contains no return receipt card indicating the date of delivery, signed by Mr. Hirani or any other company representative.
3. Defendants' Exhibit 77 contains a third page titled "ACKNOWLEDGMENT OF RECEIPT." Defs.' Ex. 77 at 3. This third page requests that an "Authorized Representative" of Hirani "sign and return this notice in the enclosed envelope." Id. Apparently, no authorized representative of Hirani formally acknowledged receipt, as the date and signature blocks are blank. Id.
4. Neither party presented any testimonial evidence as to the actual date on which the USACE sent the Termination Letter, the actual means of transmittal (e.g., certified mail, email, or fax), or the actual date on which Hirani received the Termination Letter.
5. In a letter dated April 30, 2013, Jitrendra Hirani responded to the Termination Letter. Pl.'s Ex. 151. As pertinent here, Mr. Hirani wrote: "On April 29, 2013, about 20 minutesbefore the issuance of the default termination, the USACE called Hirani to communicate, via telephone, that an interim unsatisfactory performance evaluation, among other things, was generated by the USACE's computer mailing system in late March 2013 (allowing for 30 days to respond or cure) that was never received by Hirani Engineering." Id. (emphasis added). There was no testimony about a call between the USACE and Mr. Hirani on April 29, 2013; nor did Mr. Hirani explain what he meant by receipt of a call from the USACE "about 20 minutes before the issuance of the default termination."
6. Nearly a year later, Hirani alleged in a complaint filed in the Court of Federal Claims on April 25, 2014, that it had received the Termination Letter on Monday, April 29, 2013. Pl.'s Ex. 168 at 9; see also Trial Tr., Mar. 5, 2018, PM Sess., at 32-33. There was no trial testimony as to how Hirani determined it had received the Termination Letter on that date when drafting the complaint. Absent such testimony, the complaint is weak proof of the actual date of receipt.
7. In consideration of the foregoing evidence, the court finds that Hirani received the Termination Letter no earlier than Tuesday, April 30, 2013, the date that Mr. Hirani issued the company's response letter. Defendants have not carried their burden of establishing an earlier date of receipt. See Hirani II, 962 F.3d at 593 (). Accordingly, the "effective date of the termination" of the Prime Contract, per the Federal Acquisition Regulations, is no earlier than Tuesday, April 30, 2013. See Hirani II, 962 F.3d at 593 (citing 48 C.F.R. § 2.101) (providing that "[i]f the contractor receives the termination notice after the date fixed for termination, then the effective date of termination means the date the contractor receives the notice").
8. Defendants do not assert that Hirani actually received the Termination Letter on Sunday, April 28, 2013, or earlier. See generally Defs.' Suppl. at 2-3 & n.3 ().1 Instead, they urge the court to find that the "record evidence reveals that ACC, at trial, conceded that the Corps' termination of Hirani was effective prior to April 29, 2013." Id. at 1. ACC made no such concession. Defendants cite to statements made by ACC at the summary judgment stage that the USACE "terminated" the Prime Contract on April 26, 2013, see id. at 2 (citing ECF No. 46 at 9; ECF No. 46-2 at 7, ¶ 27; ECF No. 46-3 at 8, ¶ 31), but each of those statements simply recites the fact of the date of Termination Letter. The same is true of Defendants' citation to ACC's Pre-Trial Statement, see Defs.' Suppl. at 3 (citing ECF No. 65 at 10), and ACC's opening statement at trial, see id. (citing Trial Tr., Mar. 5, 2018, AM Sess., at 8). None of those statements constitute a legal concession about the effective date of the Prime Contract's termination for statute of limitations purposes. See 32 C.J.S. Evidence § 542 (); McNamara v. Picken, 950 F. Supp. 2d 125, 129 (D.D.C. 2013) () (citation omitted).
9. ACC's Project crew performed no work on April 29, 2013. ACC's daily report for that date states in relevant part: "No work today; Rained Out Today; No possibility of work today; talked to crews at 05:45 Hours AM; No sense coming in today here; Work called due to heavyrains and such[.]" Pl.'s Ex. 31 at 928. The same report shows zero "total hours" for each person on the eight-man crew. Id. at 927.
10. ACC's Project crew likewise performed no work on April 30, 2013. ACC's daily report for that date states in relevant part: "No work today; Rained out and drizzled out; Heavy rain in morning; Lightening up in afternoon; Talked to crews in AM and jointly decided to stay home at least in AM to see what happens here; Rained out for the day completely[.]" Id. at 930. The same report shows zero "total hours" for each person on the eight-man crew. Id. at 929.
11. Ed Hollander, ACC's field superintendent for the Project, worked on April 29 and 30, 2013. According to ACC's daily reports, Hollander worked 10 hours and 11 hours, respectively, on those days. See id. at 927, 929. On both days, Hollander spent the day "in the field office on paperwork" and change orders. See id. at 928, 930. The court previously held that all of Hollander's work—including on April 29 and 30—is not compensable under the Miller Act. See United States for Use & Benefit of Am. Civil Constr., LLC v. Hirani Eng'g & Land Surveying, P.C., 345 F. Supp. 3d 11, 50 (D.D.C. 2018) ("Hirani I") (). The court reaffirms that holding here.
12. ACC "supplied material" to the Project on April 29 and 30, 2013. Hirani II, 962 F.3d at 594. This finding follows from the court's previous ruling that ACC was entitled to some compensation under the Miller Act for "standby time," that is, periods of time that ACC's owned equipment was on the Project site but not in use. See Hirani I, 345 F. Supp. 3d at 47-48. The court incorporates its prior rationale here, but also notes that its conclusion is supported by the plain text of the Miller Act and case law. The Miller Act provides a cause of action for "[e]very person that has furnished labor or material in carrying out work provided for in a contract for whicha payment bond is furnished" under the statute. 40 U.S.C. § 3133(b)(1) (emphasis added). The Miller Act does not define the term "furnish," so its plain meaning applies. "Furnish" means "to provide what is needed" or "supply, give."2 As discussed in the next paragraph, ACC provided or supplied equipment on April 29 and 30 that was needed to perform scheduled work. Additionally, U.S. ex rel. Pippin v. J.R. Youngdale Constr. Co., 923 F.2d 146 (9th Cir. 1991), which the D.C. Circuit cited on appeal, see Hirani II, 962 F.3d at 594, confirms that onsite equipment, even if idle, is "supplied" for purposes of the Miller Act's statute of limitations. In Pippin, the Ninth Circuit held that a claimant had "supplied" material "for the period that the equipment is on the project site and available for use by the subcontractor to fulfill its obligations under its contract with...
Experience vLex's unparalleled legal AI
Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting