Case Law Zafer Constr. Co. v. United States

Zafer Constr. Co. v. United States

Document Cited Authorities (11) Cited in (5) Related (1)

Abraham Gdanski, Gdanski Law PC, Teaneck, NJ, argued for plaintiff-appellant. Also represented by Sam Gdanski.

Robert R. Kiepura, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by Brian M. Boynton, Steven John Gillingham, Martin F. Hockey, Jr.

Before Newman, Reyna, and Hughes, Circuit Judges.

Hughes, Circuit Judge.

Zafer Construction Company appeals a decision of the United States Court of Federal Claims dismissing Zafer's complaint for failing to state a cause of action under Court of Federal Claims Rule 12(b)(6). The Court of Federal Claims determined that Zafer's request for equitable adjustment is not a claim under the Contract Disputes Act and that Zafer's subsequent claim is time barred. Because Zafer's request for equitable adjustment is a claim, we reverse and remand.

I

In June 2008, the United States and Zafer agreed to a $40 million contract to design and build water systems on the Bagram Air Base in Afghanistan. Zafer completed the project and submitted a request for equitable adjustment on September 10, 2013, which it timely amended on December 17, 2014. In its 167-page request, Zafer alleged that the government increased the cost of the project by causing delays and modifying the contract. Zafer's detailed request sought $6.7 million and provided a breakdown of the reasons for the claimed amounts. Zafer submitted its request "so that the parties c[ould] engage in immediate discussions and negotiations to mutually amicably resolve [its] request." Appx46 (request for equitable adjustment). And Zafer certified its request in accordance with the claim-certification requirement of 41 U.S.C. § 7103(b)(1), going beyond what is required by 48 C.F.R. § 252.243-7002(b) to certify mere requests for equitable adjustment.

The parties negotiated for four-and-a-half years but did not fully resolve Zafer's request. On February 7, 2018, Zafer asked to convert its request for equitable adjustment into a claim. The contracting officer reviewed Zafer's claim and determined that most of it is time barred under 41 U.S.C. § 7103(a)(4)(A) because much of the government's alleged conduct had transpired more than six years before Zafer had converted its request into a claim.

Zafer sued in the Court of Federal Claims. The Court of Federal Claims found that Zafer's claim had "accrued no later than August 1, 2011," meaning Zafer had to have submitted a claim by August 1, 2017 for the claim to be timely. Appx10.

Although Zafer had submitted a request for equitable adjustment in December 2014, the court determined that because this document "lacks a request for a final decision" and "asks for negotiations," it is not a claim but a request for negotiations. Appx9–10. And because Zafer converted its request for equitable adjustment into a "proper" claim after the 2017 deadline, the court dismissed Zafer's complaint for failure to state a cause of action upon which relief can be granted under the court's Rule 12(b)(6). Appx10–11.

Zafer appeals. We have jurisdiction under 28 U.S.C. § 1295(a)(3).

II

We review decisions to dismiss complaints under Rule 12(b)(6) de novo. Dehne v. United States , 970 F.2d 890, 892 (Fed. Cir. 1992).

A

The Federal Acquisition Regulation defines "claim" as

a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract.

48 C.F.R. § 52.233-1(c) ; see Todd Constr., L.P. v. United States , 656 F.3d 1306, 1311 (Fed. Cir. 2011) ("[T]he definition of the term ‘claim’ in the FAR governs" the use of that term in the Contract Disputes Act.). The regulation further distinguishes claims from "routine request[s] for payment," like vouchers or invoices. 48 C.F.R. § 52.233-1(c).

Under the Contract Disputes Act, if a contractor's claim is for more than $100,000, the contractor must certify that

(A) the claim is made in good faith;
(B) the supporting data are accurate and complete to the best of the contractor's knowledge and belief;
(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and
(D) the certifier is authorized to certify the claim on behalf of the contractor.

41 U.S.C. § 7103(b)(1) ; see 48 C.F.R. § 52.233-1(d)(2)(iii). Requests for equitable adjustment, on the other hand, require certification of only (A) and (B). 48 C.F.R. § 252.243-7002(b).

In addition to these requirements, a contractor must show that "what the contractor desires by its submissions is a final decision" from the contracting officer determining whether the contractor is entitled to the claimed amount. M. Maropakis Carpentry, Inc. v. United States , 609 F.3d 1323, 1327–28 (Fed. Cir. 2010). We have derived this "request" requirement from 41 U.S.C. § 7103(a)(1) and 48 C.F.R. § 33.206(a), which instruct contractors to submit claims "to the contracting officer for a decision. " See James M. Ellett Constr. Co. v. United States , 93 F.3d 1537, 1543 & n.4 (Fed. Cir. 1996) (emphasis added); Transamerica Ins. Corp. v. United States , 973 F.2d 1572, 1576 (Fed. Cir. 1992).

To fulfill the request requirement, the contractor's request for a final decision can be either explicit or implicit. Transamerica , 973 F.2d at 1576. The claim does not need to "be submitted in any particular form or use any particular wording." Cont. Cleaning Maint., Inc. v. United States , 811 F.2d 586, 592 (Fed. Cir. 1987). For example, a request for equitable adjustment can constitute a claim. Hejran Hejrat Co. v. U.S. Army Corps of Eng'rs , 930 F.3d 1354, 1357 (Fed. Cir. 2019). And "[t]here is no necessary inconsistency between" a claim and "an expressed desire to continue to mutually work toward a claim's resolution." Reflectone, Inc. v. Dalton , 60 F.3d 1572, 1583 (Fed. Cir. 1995).

B

The parties appear to agree that Zafer's December 2014 request for equitable adjustment satisfies the definition of a "claim" in 48 C.F.R. § 52.233-1(c) and the claim-certification requirement. See Appellee's Br. 8–10 (identifying but not disputing these requirements). At issue is whether Zafer satisfied the request requirement.

Zafer argues that its December 2014 request for equitable adjustment fulfills the request requirement because the document at length discusses Zafer's request for money owed, showing that Zafer intended for the contracting officer to make a decision regarding entitlement. Zafer contends that the Court of Federal Claims' contrary conclusion relies on a "hyper-technical analysis" that Zafer asserts we have previously rejected. Appellant's Br. 8.

The government responds that Zafer "sent clear signals" that it intended only to negotiate a contract proposal, not to request a final decision. Appellee's Br. 10. In the government's view, Zafer knew the difference between a request for equitable adjustment and a claim because Zafer submitted a proper, but untimely, claim in December 2018.

C

The parties suggest that the request requirement focuses on a contractor's subjective intent. See Appellant's Br. 11 (arguing that the length of the request for equitable adjustment evinces Zafer's "intent for the contracting officer [to] make a decision for entitlement"); Appellee's Br. 10 ("Zafer sent clear signals that, before 2018, it sought only to negotiate a contract proposal and not to seek a COFD."). That is incorrect. The determination focuses on whether, objectively, the document's content and the context surrounding the document's submission put the contracting officer on notice that the document is a claim requesting a final decision. See Heyl & Patterson, Inc. v. O'Keefe , 986 F.2d 480, 483 ("[A] request for a final decision can be implied from the context of the submission."), overruled in part on other grounds by Reflectone , 60 F.3d at 1579 n.10 ; see also Transamerica , 973 F.2d at 1576 ("[A]s long as what the contractor desires by its submissions is a final decision, that prong of the CDA claim test is met." (emphasis added)); Maropakis , 609 F.3d at 1328 ("A claim cannot be based merely on intent to assert a claim without any communication by the contractor of a desire for a contracting officer decision.").

The request requirement is not a hyper-technical requirement, and we have repeatedly rebuffed attempts to make it one, relying instead on a "common sense analysis." Transamerica , 973 F.2d at 1579.

In Contract Cleaning Maintenance, Inc. v. United States , 811 F.2d 586 (Fed. Cir. 1987), the appellant submitted letters "specif[ying] various items that ... had [been] disallowed but to which the appellant claimed entitlement" and "express[ing] the hope that the dispute could be settled." Id. at 592. The government argued that the letters were not claims because they did not "contain the requisite demand for payment as a matter of right." Id. We rejected this argument, stating that "[w]e know of no requirement in the Disputes Act that a ‘claim’ must be submitted in any particular form or use any particular wording." Id. "All that is required is that the contractor submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim." Id. We clarified that "[t]he fact that in those letters the appellant frequently expressed the hope that the dispute could be settled and suggested meeting to accomplish that result does not mean that those letters did not constitute ‘claims.’ " Id.

In Transamerica Insurance Corp., Inc. v. United States , 973 F.2d 1572 (Fed. Cir. 1992), the appellant had submitted a letter with a...

4 cases
Document | U.S. Claims Court – 2023
MidAtlantic Constr. & Design Assocs. v. United States
"...contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor." Id. (quoting 41 U.S.C. § 7103(b)(1); citing C.F.R. § 52.233-1(d)(2)(iii)).[5]Finally, while no magic language is required, the contractor must request..."
Document | U.S. Claims Court – 2023
MidAtl. Constr. & Design Assocs. v. United States
"...contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor." Id. (quoting 41 U.S.C. § 7103(b)(1); citing C.F.R. § 52.233-1(d)(2)(iii)).[5]Finally, while no magic language is required, the contractor must request..."
Document | U.S. Claims Court – 2024
Wolf Creek R.R. v. United States
"...but the contractor must unequivocally seek the CO's final decision addressing the contractor's claim for its alleged losses. Zafer, 40 F.4th at 1369 (finding persuasive sworn statement attesting to the truth of the submission, includ[ing] detailed factual bases for its alleged losses, and ...."
Document | U.S. Claims Court – 2024
MLB Transp. v. United States
"...submission is a final decision' from the contracting officer determining whether the contractor is entitled to the claimed amount." Zafer, 40 F.4th at 1367 (quoting M. Carpentry, Inc. v. United States, 609 F.3d 1323, 1327-28 (Fed. Cir. 2010)). MLB's January 10, 2014, letter does not demonst..."

Try vLex and Vincent AI for free

Start a free trial
1 firm's commentaries
Document | Mondaq United States – 2025
Surfin' CDA: Finding "Good Vibrations" In Contract DisputeV Act Case Law Developments From The Second Half Of 2024
"...tropical getaway themes to beat the winter blues away. Surf's Up! Is It A Pina Colada (Claim) Or Just A Coconut (REA)? The Boards Apply Zafer's Objective The second half of 2024 brought two different applications of the U.S. Court of Appeals for Federal Circuit's splashy Zafer Construction ..."

Try vLex and Vincent AI for free

Start a free trial

Experience vLex's unparalleled legal AI

Access millions of documents and let Vincent AI power your research, drafting, and document analysis — all in one platform.

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
4 cases
Document | U.S. Claims Court – 2023
MidAtlantic Constr. & Design Assocs. v. United States
"...contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor." Id. (quoting 41 U.S.C. § 7103(b)(1); citing C.F.R. § 52.233-1(d)(2)(iii)).[5]Finally, while no magic language is required, the contractor must request..."
Document | U.S. Claims Court – 2023
MidAtl. Constr. & Design Assocs. v. United States
"...contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor." Id. (quoting 41 U.S.C. § 7103(b)(1); citing C.F.R. § 52.233-1(d)(2)(iii)).[5]Finally, while no magic language is required, the contractor must request..."
Document | U.S. Claims Court – 2024
Wolf Creek R.R. v. United States
"...but the contractor must unequivocally seek the CO's final decision addressing the contractor's claim for its alleged losses. Zafer, 40 F.4th at 1369 (finding persuasive sworn statement attesting to the truth of the submission, includ[ing] detailed factual bases for its alleged losses, and ...."
Document | U.S. Claims Court – 2024
MLB Transp. v. United States
"...submission is a final decision' from the contracting officer determining whether the contractor is entitled to the claimed amount." Zafer, 40 F.4th at 1367 (quoting M. Carpentry, Inc. v. United States, 609 F.3d 1323, 1327-28 (Fed. Cir. 2010)). MLB's January 10, 2014, letter does not demonst..."

Try vLex and Vincent AI for free

Start a free trial

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your 3-day Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
1 firm's commentaries
Document | Mondaq United States – 2025
Surfin' CDA: Finding "Good Vibrations" In Contract DisputeV Act Case Law Developments From The Second Half Of 2024
"...tropical getaway themes to beat the winter blues away. Surf's Up! Is It A Pina Colada (Claim) Or Just A Coconut (REA)? The Boards Apply Zafer's Objective The second half of 2024 brought two different applications of the U.S. Court of Appeals for Federal Circuit's splashy Zafer Construction ..."

Try vLex and Vincent AI for free

Start a free trial